Renewal Progress - January 2021
31 January 2021 16:17
General. Most of the scaffolding in the Nave, the north and south aisles, the chapels and the crossing were taken down. A scaffold was erected to limewash the accessible walls either side of the organ. |
Electrical works. Wiring for the dais was installed. Sockets and appliances were connected in the kitchen. |
Heating works. A start was made on the new heating pipework in the Nave. |
Toilet. Most of the plastering and floor finishes were completed and ventilation fans installed. |
Dais. Work started on the dais. The floor strengthening was completed and most of the dais framework was constructed. |
Kitchen. All the units and worktops were fitted. The ovens were installed. See also electrical works. |
Lighting. Minor installations only. |
Plaster/stonework repairs. Final plaster repairs completed |
Limewashing. Limewashing at high level was completed allowing the scaffolding to be brought down. |
Ringing Chamber Screen. Steelwork was completed: further progress awaits delivery of glass panels. The heating unit for the ringing chamber was installed. |
Flooring. Floor strengthening was carried out below the dais and the pulpit areas. |
Other. No work |
Lady Chapel. No work |